Name |
Rålambshovsleden/Norr Mälarstrand |
Location |
Stockholm |
Client |
Stockholm City, Traffic Office, Construction Department Mats Larsson, Civil Engineering Box 8311, 104 20 Stockholm Phone: 08-508 263 66 / 076-12 263 66 Email: mats.t.larsson@stockholm.se |
Mission time |
Dec 2015 – Dec 2016 |
Role/Task |
Assignment Manager: Cost Estimation, Quantity and Calculation |
Project cost |
ca. 30 mnkr |
Mission statement |
The reconstruction of the pedestrian and bicycle path through Rålambshovsparken as well as renovating the tunnel under Gjörwellsgatan in Kungsholmen. The bi-directional cycle path will be widened up to 4.5 meters. Lighting posts, electrical cabinets and cables are put in new positions to adapt to the new design of the walkways. New lighting in the tunnel. The cost estimate has been prepared at several stages in the project, from idea to construction document. |
Experience from the assignment |
|
Link to project |
https://xn--vxer-loa.stockholm/projekt/breddad-cykelvag-vid-norr-malarstrand/ |